On the NJ Water Supply Authority’s web site, from the most recent meeting minutes (Oct. 2015):
“The refurbishment of Pump Assemblies #1 & #6 are completed. The pumps have been returned to the South Branch Pumping Station. The contractor has started the installation of the base plates. Once in place, the pumps & motors can be installed & prepared for testing.”
If the tests go ok, I imagine that they would start pumping in the spring (2016) as they usually do, when the flows are historically higher.
|